top of page
MV Tienstin
Repairs to damaged crane jib
> Land maxi boom onto ships decking and lift equipment onto working platform
> Secure crane jib and reinforce top section of crane jib to cab tower
> Cut out damaged section of jib and prep for welding
> Carry out repairs to internal gussets and re-weld
> Insert backing strips and install new plates
> Arrange for 35 ton water bags with certified load cell for load testing
Project Gallery